$EXNRF ) concentrator at Mallay, the silver-lead-zinc mine in central Peru 🇵🇪, restarted on a pre-commissioning basis July 2, 2026. Roughly 12,000 tonnes processed with no unplanned plant shutdowns.
$EXN $EXN.V
$EXNRF
Concentrates contain approximately 29,200 oz silver, 319,000 lb lead and 456,000 lb zinc, contained metal and not yet payable. Initial lead-silver and zinc concentrate shipments are expected in August 2026, with payment during the quarter.
Three rigs are active, and an updated restart plan and schedule is targeted for Q3 2026. Funding it: US
$14.8M cash as at the May 27 release plus US
$5.0M undrawn under the Glencore facility, with US
$6.8M invested in Mallay and Tres Cerros so far in 2026.